This is a response to a guest editorial written by State Representative Dominic LaRicc
First and foremost, the City of Douglas has the legal authority to use whichever service delivery method we determine to be the most cost effective to complete multiple capital projects. Currently, across the state of Georgia, there are at least three common approaches to construction projects: Sealed Bid (Hard Bid), Design Construction and Construction Management (with or without risk). Due to the number of projects and the short timeframe in which to deliver these projects, the City decided to explore the option of using the CMAR delivery method.
What is the CMAR delivery method? The Construction Manager at Risk (CMAR) is a delivery method which entails a commitment by the construction manager (CM) to deliver the project within a guaranteed maximum price (GMP), which is based on the construction documents and specifications at the time of the GMP plus any reasonably inferred items or tasks. The CMAR provides professional services and acts as a consultant to the City in the design development and construction phases. Often times, the CMAR also provides some of the actual construction of the project depending on the availability of bidders and the expertise the company has. In addition to acting in the City‘s interest, the CMAR must manage and control construction costs to not exceed the GMP because,contractually, any costs exceeding the GMP, that are not change orders, are the financial liability of the CMAR.
Generally, the CMAR will give the City a GMP prior to bidding the project. Included in this GMP is a contingency line item to take care of bid overages, reasonably inferred items and other project related items that may arise during construction. By giving the City the GMP prior to bids, the CMAR assumes the risk of bids coming in higher as he is contractually bound to deliver the project per the plans and specifications and any additional allowances as defined in his GMP.
City Benefits
This delivery method has several unique benefits to the City, including:
· A higher level of cost control from the start – A successful CMAR project would involve hiring the CMAR prior to the architect and having the CMAR help select the architect. During the design process, the CMAR provides cost estimates at contractually established points. If these cost estimates are in line with the established budget, the architect then moves on to the next phase of design. If not, the CMAR, City and Architect assess the cost estimate and make design changes to bring the design back into budget alignment. This process ensures budget success.
· The CMAR is a City advocate and manages the project with the City’s best interest in mind at all times.
· The CMAR takes the burden off of the City in managing and coordinating the project.
· The City’s risk is limited by the CMAR process provided that the construction documents are complete and proper allowances and contingencies are built into the GMP.
· Constructability and value to the City are afforded by the value engineering expertise brought to the process by the CMAR.
· Since the CMAR is at risk and gives the GMP prior to bid, the CM does not have to select the low bid. Generally the thorough prequalification process minimizes the number of lowbidders that get disqualified and generally leads to lower long term costs, higher quality, and fewer claims because only pre-qualified contractors are performing work.
· CMAR services are professional services like architectural, engineering, surveying, etc. The CMAR’s main purpose is not to construct the project, but to manage the construction of the project. This management focus adds much value to the project.
As with any delivery method, incomplete and/or inaccurate construction drawings will result in change orders. The misunderstanding associated with the GMP is that this maximum price will not be exceeded in any case. It is important to understand that the GMP is based on the plans and specifications at the time of the GMP with some reasonable assumptions made and a reasonable contingency included. Major changes in scope will result in a change order, which increases the GMP contract. In addition, any City changes to the project and scope require a change order. By requiring the documents be 100 percent complete prior to receiving the GMP, the risk of unanticipated change orders are minimized.
As stated in the editorial, we admit that there were some words in the RFP that seemed to be confusing and needed to be clarified. Also, we should have termed the document an RFQ/P as well. Nevertheless, the document needed to be changed to clearly articulate our position and what we want out of a CMAR provider. A pre-qualification meeting was held on October 13, 2017,which was mandatory for submittal. At this meeting, we were seeking to gather input from the interested vendors to clarify andaddress questions about our expectations of the awarded firm.As of today, we have taken most of the questions, concerns and comments provided by proposing vendors to revise the RFQ/P. The revised RFQ/P will be sent out this week, along with minutes from the pre-qualification meeting and other related information to help each vendor respond appropriately to the City’s expectations for CMAR.
It is the intention of the City of Douglas to complete the RFQ/P process to determine if this should be the delivery method usedto
The City of Douglas is committedto having these eigh
We appreciate Representative LaRiccia and others in thecommunity who have expressed concerns regarding this major decision for the City of Douglas. Therefore, we will consider these issues as we move forward with this process to be mindful of these concerns and be vigilant in our deliberation of this process.